The complex LTCS and duplex bore spools fabrication included:

– 750 NB Piping heavy wall piping
– 100+ welded joints completed with minimal weld repairs
– TIG, FCAW, SAW and TIP-TIG welding techniques utilised
– Humidur coating applied
– Hot work insulation

Fabrication of the large pipe bridges and structures included:

– > 60 tonne Plus trestles and pipe bridges
– L0 testing and Z25 testing applied to all material
– 100+ Pipe supports
– Surveyed structure for easy install on site

The spools fabrication was complex, with weld procedure specifications required for duplex/carbon overlay welding and an acute focus on quality was maintained throughout to achieve the desired result.

The fabrication was completed over of 20,000+ man hours with Zero LTI’s.

CASE STUDIES

Turnaround Maintenance Project for LNG Upstream and Downstream

The Project The second of the planned turnaround maintenance programs for a key LNG operator in…

Sino Iron Project Power Plant – Thermal Insulation

The scope involved the application of thermal insulation and cladding to piping and equipment for the…

CBH Ship Loader Refurbishment Contract

AGC was contracted to refurbish Ship Loaders 3 and 4 at Kwinana for CBH. The scope…