









The complex LTCS and duplex bore spools fabrication included:
– 750 NB Piping heavy wall piping
– 100+ welded joints completed with minimal weld repairs
– TIG, FCAW, SAW and TIP-TIG welding techniques utilised
– Humidur coating applied
– Hot work insulation
Fabrication of the large pipe bridges and structures included:
– > 60 tonne Plus trestles and pipe bridges
– L0 testing and Z25 testing applied to all material
– 100+ Pipe supports
– Surveyed structure for easy install on site
The spools fabrication was complex, with weld procedure specifications required for duplex/carbon overlay welding and an acute focus on quality was maintained throughout to achieve the desired result.
The fabrication was completed over of 20,000+ man hours with Zero LTI’s.
CASE STUDIES
Chevron Potable Water Project
Fabrication, painting, insultation and installation of : 7.5km of pipeline, 300 spools, 100 tonne of…
Wheatstone onshore and offshore turnaround (TAR 501)
AusGroup was awarded the Primary Maintenance Contract (PMC) for the delivery of Wheatstone’s first major…
Gorgon Reliable Instrument Air Generation (RIAG) Project
AusGroup were awarded the fabrication of the modules for the Reliable Instrument Air Generation (RIAG) Project…