The ShoemakerLevy project involves the expansion into a second stage nickel laterite deposit which will give RNO a LOM of approximately 30 years.

The scope involves the full assembly, alignment, construction verification and preparation for shipment for all 33 prefabricated truss sections.

Each of the sections were fabricated overseas and shipped to AGC’s Kwinana facility where they were organised, assembled and outfitted with grating, handrail and idler rollers.