Peak Manning:   60+
Pricing Model:   Norms Estimate
Project Metrics:

  • Original budget estimated hours per train: 26,647.74hrs
  • Train 3 Actual hours: 26,626.36hrs (21.38hrs saved)
  • Train 2 Actual hours: 21,877.52hrs (4,770.22hrs saved)
  • Train 1 Actual hours: 20,001.27hrs (6,646.47hrs saved)
  • Total hours saved: 11,438.07hrs

 

Continuous Improvement Initiatives

  • SIMOPS with other contractors was achieved by implementation of daily meetings, addressing all relevant planned activities and discussing opportunities for improvement where possible.
  • In the pre-planning phase, requesting the required data from other disciplines, such as weld maps & NDT reports to optimize resource scheduling and work front availability.

CASE STUDIES

Chevron Potable Water Project

  Fabrication, painting, insultation and installation of : 7.5km of pipeline, 300 spools, 100 tonne of…

Tianqi Lithium – Kwinana Lithium Hydroxide Processing Plant

Aus Group was awarded a contract to provide piping and insulation works on the LHPP1 Crystalliser…

Turnaround Maintenance Project for LNG Upstream and Downstream

The Project The second of the planned turnaround maintenance programs for a key LNG operator in…