Further to this AGC were chosen because of our multi discipline capabilities, AGC has reduced the cost to Chevron by reducing the number of overall personnel on site.

We are able to execute the scope from demolition through to insulation, and everything in between, as well as finish with commissioning of the new header. This has increased efficiency and reduced the overall duration as there’s no interface between multiple contractors.

Peak Manning: 29 (include Indirects)

Pricing Model: Target Cost Estimate (utilisig Norms)

Project Metrics: On handover from Downer – 3.9h/m. Currently 2.97h/m